BetaActiveSolarBatteryBPALBNL
600 MW hybrid in Deschutes, OR · In queue since December 2020 · Proposed COD December 2025
600 MW
Capacity
2
Components
Solar + Battery
5y 3m
In Queue
In Progress (unknown study)
IA Status
COD target: 2025
Interconnection Timeline
Total Duration
5 years
Schedule
4 months past proposed COD
In Study38%
Queue EntryDec 21, 2020
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2025-12-01
Technology
Solar400 MW · 67%
Battery200 MW · 33%
Project Details
State
OR
County
Deschutes
Region
West
Developer
—
Utility
Bonneville Power Administration
Entity
BPA
Point of Interconnection
Pilot Butte to Redmond 230kV or Pilot Butte to Ponderosa 230kV
Data Source
LBNL
No news available for this project.