BetaActiveSolarBatteryBPALBNL
300 MW hybrid in Grant, WA · In queue since November 2020 · Proposed COD October 2024
300 MW
Capacity
2
Components
Solar + Battery
5y 4m
In Queue
In Progress (unknown study)
IA Status
COD target: 2024
Interconnection Timeline
Total Duration
3y 11m
Schedule
18 months past proposed COD
In Study38%
Queue EntryNov 5, 2020
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2024-10-01
Technology
Solar200 MW · 67%
Battery100 MW · 33%
Project Details
State
WA
County
Grant
Region
West
Developer
—
Utility
Bonneville Power Administration
Entity
BPA
Point of Interconnection
POI 1: Grand Coulee - Rocky Ford 230 kV POI 2: Grand Coulee - Potholes 230 kV
Data Source
LBNL