BetaActiveBatteryBPALBNL
500 MW storage in Grant, WA · In queue since September 2020 · Proposed COD November 2023
500 MW
Capacity
1
Components
Battery
5y 6m
In Queue
In Progress (unknown study)
IA Status
COD target: 2023
Interconnection Timeline
Total Duration
3y 2m
Schedule
28 months past proposed COD
In Study38%
Queue EntrySep 16, 2020
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2023-11-30
Project Details
State
WA
County
Grant
Region
West
Developer
—
Utility
Bonneville Power Administration
Entity
BPA
Point of Interconnection
BPA's Vantage 230 kV Substation
Data Source
LBNL
No news available for this project.