170 MW generation in Lake, OR · In queue since August 2020 · Proposed COD January 2027
170 MW
Capacity
1
Components
Solar
5y 7m
In Queue
In Progress (unknown study)
IA Status
COD target: 2027
Interconnection Timeline
Total Duration
6y 5m
In Study38%
Queue EntryAug 31, 2020
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2027-01-01
Project Details
State
OR
County
Lake
Region
West
Developer
—
Utility
Bonneville Power Administration
Entity
BPA
Point of Interconnection
La Pine - Fort Rock No 1 115 kV line.
Data Source
LBNL