— Project Summary

Queue ID
BPA-G0651
Capacity
400 MW
Technology
Solar
Status
active
Location
Lake, OR
Region
West
Developer
IA Status
In Progress (unknown study)

BetaActiveSolarBPALBNL

400 MW generation in Lake, OR · In queue since July 2020 · Proposed COD September 2023

400 MW

Capacity

1

Components

Solar

5y 8m

In Queue

In Progress (unknown study)

IA Status

COD target: 2023

Interconnection Timeline

Total Duration

3y 2m

Schedule

30 months past proposed COD

In Study38%
Queue EntryJul 8, 2020

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2023-09-30

Project Details

State

OR

County

Lake

Region

West

Developer

Utility

Bonneville Power Administration

Entity

BPA

Point of Interconnection

Grizzly-Summer Lake No 1 500 kV line

Data Source

LBNL