BetaActiveSolarBPALBNL
200 MW generation in Klickitat, WA · In queue since March 2020 · Proposed COD January 2026
200 MW
Capacity
1
Components
Solar
6 years
In Queue
Facility Study
IA Status
COD target: 2026
Interconnection Timeline
Total Duration
5y 10m
Schedule
2 months past proposed COD
Facilities Study50%
Queue EntryMar 23, 2020
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2026-01-31
Project Details
State
WA
County
Klickitat
Region
West
Developer
—
Utility
Bonneville Power Administration
Entity
BPA
Point of Interconnection
McNary-John Day 500kV Tap (BPA's "G0585 Substation")
Data Source
LBNL
No news available for this project.