— Project Summary

Queue ID
BPA-G0645
Capacity
200 MW
Technology
Solar
Status
active
Location
Klickitat, WA
Region
West
Developer
IA Status
Facility Study

BetaActiveSolarBPALBNL

200 MW generation in Klickitat, WA · In queue since March 2020 · Proposed COD January 2026

200 MW

Capacity

1

Components

Solar

6 years

In Queue

Facility Study

IA Status

COD target: 2026

Interconnection Timeline

Total Duration

5y 10m

Schedule

2 months past proposed COD

Facilities Study50%
Queue EntryMar 23, 2020

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2026-01-31

Project Details

State

WA

County

Klickitat

Region

West

Developer

Utility

Bonneville Power Administration

Entity

BPA

Point of Interconnection

McNary-John Day 500kV Tap (BPA's "G0585 Substation")

Data Source

LBNL

No news available for this project.