BetaActiveBatteryBPALBNL
600 MW storage in Crook, OR · In queue since February 2020 · Proposed COD June 2024
600 MW
Capacity
1
Components
Battery
6y 1m
In Queue
In Progress (unknown study)
IA Status
COD target: 2024
Interconnection Timeline
Total Duration
4y 4m
Schedule
22 months past proposed COD
In Study38%
Queue EntryFeb 24, 2020
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2024-06-01
Project Details
State
OR
County
Crook
Region
West
Developer
—
Utility
Bonneville Power Administration
Entity
BPA
Point of Interconnection
Ponderosa 230 kV
Data Source
LBNL