239 MW generation in Klamath, OR · In queue since February 2020 · Proposed COD December 2025
239 MW
Capacity
1
Components
Wind
6y 1m
In Queue
In Progress (unknown study)
IA Status
COD target: 2025
Total Duration
5y 10m
Schedule
3 months past proposed COD
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2025-12-31
State
OR
County
Klamath
Region
West
Developer
—
Utility
Bonneville Power Administration
Entity
BPA
Point of Interconnection
Option I: New 230 kV point onto BPA's existing 500 kV Captain Jack Substation; Option 2: New 230 kV point onto BPA's existing Malin Substation; Option 3: New 230 kV facility adjacent to BPA's Malin Hilltop 230 kV line, approx. adjacent to the Malin Substation
Data Source
LBNL