200 MW generation in Douglas, WA · In queue since February 2020 · Proposed COD August 2023
200 MW
Capacity
1
Components
Solar
6y 1m
In Queue
In Progress (unknown study)
IA Status
COD target: 2023
Interconnection Timeline
Total Duration
3y 6m
Schedule
32 months past proposed COD
In Study38%
Queue EntryFeb 3, 2020
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2023-08-01
Project Details
State
WA
County
Douglas
Region
West
Developer
—
Utility
Bonneville Power Administration
Entity
BPA
Point of Interconnection
BPA's Rocky Reach - Columbia 230 kV line.
Data Source
LBNL
No news available for this project.