BetaActiveWindBPALBNL
100 MW generation in Benton, WA · In queue since January 2020 · Proposed COD October 2021
100 MW
Capacity
1
Components
Wind
6y 2m
In Queue
Facility Study
IA Status
COD target: 2021
Interconnection Timeline
Total Duration
1y 9m
Schedule
55 months past proposed COD
Facilities Study50%
Queue EntryJan 7, 2020
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2021-10-01
Project Details
State
WA
County
Benton
Region
West
Developer
—
Utility
Bonneville Power Administration
Entity
BPA
Point of Interconnection
Franklin - McNary 230 KV transmission line.