— Project Summary

Queue ID
BPA-G0626
Capacity
90 MW
Technology
Solar
Status
active
Location
Grant, WA
Region
West
Developer
IA Status
Facility Study

BetaActiveSolarBPALBNL

90 MW generation in Grant, WA · In queue since June 2019 · Proposed COD December 2022

90 MW

Capacity

1

Components

Solar

6y 9m

In Queue

Facility Study

IA Status

COD target: 2022

Interconnection Timeline

Total Duration

3y 6m

Schedule

39 months past proposed COD

Facilities Study50%
Queue EntryJun 27, 2019

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2022-12-31

Project Details

State

WA

County

Grant

Region

West

Developer

Utility

Bonneville Power Administration

Entity

BPA

Point of Interconnection

Vantage Substation 230 kV

Data Source

LBNL

No news available for this project.