BetaActiveSolarBPALBNL
90 MW generation in Grant, WA · In queue since June 2019 · Proposed COD December 2022
90 MW
Capacity
1
Components
Solar
6y 9m
In Queue
Facility Study
IA Status
COD target: 2022
Interconnection Timeline
Total Duration
3y 6m
Schedule
39 months past proposed COD
Facilities Study50%
Queue EntryJun 27, 2019
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2022-12-31
Project Details
State
WA
County
Grant
Region
West
Developer
—
Utility
Bonneville Power Administration
Entity
BPA
Point of Interconnection
Vantage Substation 230 kV
Data Source
LBNL