BetaActiveGasBPALBNL
27 MW generation in Umatilla, OR · In queue since April 2019 · Proposed COD October 2019
27 MW
Capacity
1
Components
Gas
6y 11m
In Queue
In Progress (unknown study)
IA Status
COD target: 2019
Interconnection Timeline
Total Duration
6 months
Schedule
78 months past proposed COD
In Study38%
Queue EntryApr 11, 2019
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2019-10-31
Project Details
State
OR
County
Umatilla
Region
West
Developer
—
Utility
Bonneville Power Administration
Entity
BPA
Point of Interconnection
Coyote Springs Substation
Data Source
LBNL
No news available for this project.