— Project Summary

Queue ID
BPA-G0619
Capacity
500 MW
Technology
Wind
Status
active
Location
Wasco, OR
Region
West
Developer
IA Status
In Progress (unknown study)

BetaActiveWindBPALBNL

500 MW generation in Wasco, OR · In queue since April 2019 · Proposed COD December 2023

500 MW

Capacity

1

Components

Wind

6y 11m

In Queue

In Progress (unknown study)

IA Status

COD target: 2023

Interconnection Timeline

Total Duration

4y 8m

Schedule

27 months past proposed COD

In Study38%
Queue EntryApr 10, 2019

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2023-12-31

Project Details

State

OR

County

Wasco

Region

West

Developer

Utility

Bonneville Power Administration

Entity

BPA

Point of Interconnection

Primary: Slatt to John Day 500 kV transmission line. Alternate: Diamond Butte Substation

Data Source

LBNL

No news available for this project.