300 MW hybrid in Sherman, OR · In queue since March 2019 · Proposed COD August 2022
300 MW
Capacity
2
Components
Solar + Battery
7 years
In Queue
In Progress (unknown study)
IA Status
COD target: 2022
Interconnection Timeline
Total Duration
3y 5m
Schedule
44 months past proposed COD
In Study38%
Queue EntryMar 22, 2019
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2022-08-01
Technology
Solar200 MW · 67%
Battery100 MW · 33%
Project Details
State
OR
County
Sherman
Region
West
Developer
—
Utility
Bonneville Power Administration
Entity
BPA
Point of Interconnection
John Day No 2 230 kV transmission line or Biglow Canyon Substation.