BetaActiveSolarBatteryBPALBNL
1,200 MW hybrid in Sherman, OR · In queue since February 2019 · Proposed COD December 2021
1,200 MW
Capacity
2
Components
Solar + Battery
7y 1m
In Queue
Facility Study
IA Status
COD target: 2021
Interconnection Timeline
Total Duration
2y 10m
Schedule
52 months past proposed COD
Facilities Study50%
Queue EntryFeb 21, 2019
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2021-12-31
Technology
Solar800 MW · 67%
Battery400 MW · 33%
Project Details
State
OR
County
Sherman
Region
West
Developer
—
Utility
Bonneville Power Administration
Entity
BPA
Point of Interconnection
Slatt - Buckley No 1 500 kV transmission line, approximately 10 miles from Buckley Substation.
Data Source
LBNL
No news available for this project.