— Project Summary

Queue ID
BPA-G0615
Capacity
1200 MW
Technology
Solar+Battery
Status
active
Location
Sherman, OR
Region
West
Developer
IA Status
Facility Study

BetaActiveSolarBatteryBPALBNL

1,200 MW hybrid in Sherman, OR · In queue since February 2019 · Proposed COD December 2021

1,200 MW

Capacity

2

Components

Solar + Battery

7y 1m

In Queue

Facility Study

IA Status

COD target: 2021

Interconnection Timeline

Total Duration

2y 10m

Schedule

52 months past proposed COD

Facilities Study50%
Queue EntryFeb 21, 2019

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2021-12-31

Technology
Solar800 MW · 67%
Battery400 MW · 33%
Project Details

State

OR

County

Sherman

Region

West

Developer

Utility

Bonneville Power Administration

Entity

BPA

Point of Interconnection

Slatt - Buckley No 1 500 kV transmission line, approximately 10 miles from Buckley Substation.

Data Source

LBNL

No news available for this project.