— Project Summary

Queue ID
BPA-G0609
Capacity
400 MW
Technology
Battery
Status
active
Location
Multnomah, OR
Region
West
Developer
IA Status
Facility Study

BetaActiveBatteryBPALBNL

400 MW storage in Multnomah, OR · In queue since December 2018 · Proposed COD December 2021

400 MW

Capacity

1

Components

Battery

7y 3m

In Queue

Facility Study

IA Status

COD target: 2021

Interconnection Timeline

Total Duration

3 years

Schedule

52 months past proposed COD

Facilities Study50%
Queue EntryDec 21, 2018

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2021-12-31

Project Details

State

OR

County

Multnomah

Region

West

Developer

Utility

Bonneville Power Administration

Entity

BPA

Point of Interconnection

Troutdale 230kV Substation

Data Source

LBNL

No news available for this project.