— Project Summary

Queue ID
BPA-G0608
Capacity
1200 MW
Technology
Battery
Status
active
Location
Klickitat, WA
Region
West
Developer
IA Status
In Progress (unknown study)

BetaActiveBatteryBPALBNL

1,200 MW storage in Klickitat, WA · In queue since December 2018 · Proposed COD December 2027

1,200 MW

Capacity

1

Components

Battery

7y 3m

In Queue

In Progress (unknown study)

IA Status

COD target: 2027

Interconnection Timeline

Total Duration

9 years

In Study38%
Queue EntryDec 7, 2018

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2027-12-31

Project Details

State

WA

County

Klickitat

Region

West

Developer

Utility

Bonneville Power Administration

Entity

BPA

Point of Interconnection

BPA's John Day 500 kV Substation

Data Source

LBNL

No news available for this project.