— Project Summary

Queue ID
BPA-G0602
Capacity
170 MW
Technology
Solar
Status
active
Location
Grant, WA
Region
West
Developer
IA Status
Facility Study

BetaActiveSolarBPALBNL

170 MW generation in Grant, WA · In queue since October 2018 · Proposed COD December 2022

170 MW

Capacity

1

Components

Solar

7y 5m

In Queue

Facility Study

IA Status

COD target: 2022

Interconnection Timeline

Total Duration

4y 2m

Schedule

39 months past proposed COD

Facilities Study50%
Queue EntryOct 17, 2018

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2022-12-31

Project Details

State

WA

County

Grant

Region

West

Developer

Utility

Bonneville Power Administration

Entity

BPA

Point of Interconnection

Vantage Substation 230 kV

Data Source

LBNL