BetaActiveSolarBPALBNL
1 MW generation in Lane, OR · In queue since July 2018 · Proposed COD September 2018
1 MW
Capacity
1
Components
Solar
7y 8m
In Queue
In Progress (unknown study)
IA Status
COD target: 2018
Interconnection Timeline
Total Duration
2 months
Schedule
91 months past proposed COD
In Study38%
Queue EntryJul 18, 2018
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2018-09-21
Project Details
State
OR
County
Lane
Region
West
Developer
—
Utility
Bonneville Power Administration
Entity
BPA
Point of Interconnection
EWEB's system. Exact location TBD.
Data Source
LBNL