— Project Summary

Queue ID
BPA-G0594
Capacity
1 MW
Technology
Solar
Status
active
Location
Lane, OR
Region
West
Developer
IA Status
In Progress (unknown study)

BetaActiveSolarBPALBNL

1 MW generation in Lane, OR · In queue since July 2018 · Proposed COD September 2018

1 MW

Capacity

1

Components

Solar

7y 8m

In Queue

In Progress (unknown study)

IA Status

COD target: 2018

Interconnection Timeline

Total Duration

2 months

Schedule

91 months past proposed COD

In Study38%
Queue EntryJul 18, 2018

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2018-09-21

Project Details

State

OR

County

Lane

Region

West

Developer

Utility

Bonneville Power Administration

Entity

BPA

Point of Interconnection

EWEB's system. Exact location TBD.

Data Source

LBNL

No news available for this project.