BetaActiveSolarBPALBNL
381 MW generation in Klickitat, WA · In queue since May 2018 · Proposed COD December 2023
381 MW
Capacity
1
Components
Solar
7y 10m
In Queue
Facility Study
IA Status
COD target: 2023
Interconnection Timeline
Total Duration
5y 7m
Schedule
27 months past proposed COD
Facilities Study50%
Queue EntryMay 25, 2018
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2023-12-31
Project Details
State
WA
County
Klickitat
Region
West
Developer
—
Utility
Bonneville Power Administration
Entity
BPA
Point of Interconnection
Knight 500 kV Substation
Data Source
LBNL
No news available for this project.