BetaActiveSolarBPALBNL
100 MW generation in Klickitat, WA · In queue since April 2018 · Proposed COD June 2022
100 MW
Capacity
1
Components
Solar
7y 11m
In Queue
Facility Study
IA Status
COD target: 2022
Interconnection Timeline
Total Duration
4y 2m
Schedule
46 months past proposed COD
Facilities Study50%
Queue EntryApr 6, 2018
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2022-06-15
Project Details
State
WA
County
Klickitat
Region
West
Developer
—
Utility
Bonneville Power Administration
Entity
BPA
Point of Interconnection
BPA's Spring Creek 230 kV Substation.
Data Source
LBNL