— Project Summary

Queue ID
BPA-G0585
Capacity
313 MW
Technology
Wind
Status
active
Location
Klickitat, WA
Region
West
Developer
IA Status
In Progress (unknown study)

BetaActiveWindBPALBNL

313 MW generation in Klickitat, WA · In queue since March 2018 · Proposed COD July 2021

313 MW

Capacity

1

Components

Wind

8 years

In Queue

In Progress (unknown study)

IA Status

COD target: 2021

Interconnection Timeline

Total Duration

3y 4m

Schedule

58 months past proposed COD

In Study38%
Queue EntryMar 19, 2018

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2021-07-01

Project Details

State

WA

County

Klickitat

Region

West

Developer

Utility

Bonneville Power Administration

Entity

BPA

Point of Interconnection

McNary-John Day 500kV Tap (BPA's "G0585 Substation")

Data Source

LBNL