BetaActiveSolarBatteryBPALBNL
160 MW hybrid in Yakima, WA · In queue since November 2017 · Proposed COD November 2022
160 MW
Capacity
2
Components
Solar + Battery
8y 4m
In Queue
Facility Study
IA Status
COD target: 2022
Interconnection Timeline
Total Duration
5 years
Schedule
41 months past proposed COD
Facilities Study50%
Queue EntryNov 2, 2017
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2022-11-01
Technology
Solar80 MW · 50%
Battery80 MW · 50%
Project Details
State
WA
County
Yakima
Region
West
Developer
—
Utility
Bonneville Power Administration
Entity
BPA
Point of Interconnection
BPA's Midway - Moxee 115 kV transmission line.
Data Source
LBNL
No news available for this project.