— Project Summary

Queue ID
BPA-G0572
Capacity
20 MW
Technology
Solar
Status
active
Location
Lake, OR
Region
West
Developer
IA Status
In Progress (unknown study)

BetaActiveSolarBPALBNL

20 MW generation in Lake, OR · In queue since July 2017 · Proposed COD June 2019

20 MW

Capacity

1

Components

Solar

8y 8m

In Queue

In Progress (unknown study)

IA Status

COD target: 2019

Interconnection Timeline

Total Duration

1y 11m

Schedule

83 months past proposed COD

In Study38%
Queue EntryJul 31, 2017

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2019-06-01

Project Details

State

OR

County

Lake

Region

West

Developer

Utility

Bonneville Power Administration

Entity

BPA

Point of Interconnection

Midstate Electric's Fort Rock 115 kV Substation.

Data Source

LBNL

No news available for this project.