BetaActiveSolarBPALBNL
20 MW generation in Lake, OR · In queue since July 2017 · Proposed COD June 2019
20 MW
Capacity
1
Components
Solar
8y 8m
In Queue
In Progress (unknown study)
IA Status
COD target: 2019
Interconnection Timeline
Total Duration
1y 11m
Schedule
83 months past proposed COD
In Study38%
Queue EntryJul 31, 2017
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2019-06-01
Project Details
State
OR
County
Lake
Region
West
Developer
—
Utility
Bonneville Power Administration
Entity
BPA
Point of Interconnection
Midstate Electric's Fort Rock 115 kV Substation.
Data Source
LBNL
No news available for this project.