BetaActiveSolarBPALBNL
20 MW generation in Lake, OR · In queue since July 2017 · Proposed COD June 2019
20 MW
Capacity
1
Components
Solar
8y 8m
In Queue
In Progress (unknown study)
IA Status
COD target: 2019
Interconnection Timeline
Total Duration
1y 11m
Schedule
83 months past proposed COD
In Study38%
Queue EntryJul 31, 2017
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2019-06-01
Project Details
State
OR
County
Lake
Region
West
Developer
—
Utility
Bonneville Power Administration
Entity
BPA
Point of Interconnection
Tap off BPA's 115 kV line within 10 miles of Midstate Electric's Fort Rock 115 kV Substation.
Data Source
LBNL
No news available for this project.