646 MW generation in Lincoln, MT · In queue since June 2017 · Proposed COD September 2022
646 MW
Capacity
1
Components
Hydro
8y 9m
In Queue
Facility Study
IA Status
COD target: 2022
Interconnection Timeline
Total Duration
5y 3m
Schedule
42 months past proposed COD
Facilities Study50%
Queue EntryJun 5, 2017
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2022-09-30
Project Details
State
MT
County
Lincoln
Region
West
Developer
—
Utility
Bonneville Power Administration
Entity
BPA
Data Source
LBNL