500 MW generation in Benton, WA · In queue since February 2017 · Proposed COD December 2019
500 MW
Capacity
1
Components
Wind
9y 1m
In Queue
Facility Study
IA Status
COD target: 2019
Interconnection Timeline
Total Duration
2y 10m
Schedule
77 months past proposed COD
Facilities Study50%
Queue EntryFeb 21, 2017
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2019-12-01
Project Details
State
WA
County
Benton
Region
West
Developer
—
Utility
Bonneville Power Administration
Entity
BPA
Point of Interconnection
BPA's Ashe - Marion 500 kV, Mile 26, Tower 4; BPA's McNary - John Day 500 kV, Mile 4, Tower 1
Data Source
LBNL
No news available for this project.