— Project Summary

Queue ID
BPA-G0558
Capacity
500 MW
Technology
Wind
Status
active
Location
Benton, WA
Region
West
Developer
IA Status
Facility Study

BetaActiveWindBPALBNL

500 MW generation in Benton, WA · In queue since February 2017 · Proposed COD December 2019

500 MW

Capacity

1

Components

Wind

9y 1m

In Queue

Facility Study

IA Status

COD target: 2019

Interconnection Timeline

Total Duration

2y 10m

Schedule

77 months past proposed COD

Facilities Study50%
Queue EntryFeb 21, 2017

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2019-12-01

Project Details

State

WA

County

Benton

Region

West

Developer

Utility

Bonneville Power Administration

Entity

BPA

Point of Interconnection

BPA's Ashe - Marion 500 kV, Mile 26, Tower 4; BPA's McNary - John Day 500 kV, Mile 4, Tower 1

Data Source

LBNL