BetaActiveWindBPALBNL
350 MW generation in Umatilla, OR · In queue since June 2016 · Proposed COD December 2019
350 MW
Capacity
1
Components
Wind
9y 9m
In Queue
Facility Study
IA Status
COD target: 2019
Interconnection Timeline
Total Duration
3y 6m
Schedule
76 months past proposed COD
Facilities Study50%
Queue EntryJun 6, 2016
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2019-12-31
Project Details
State
OR
County
Umatilla
Region
West
Developer
—
Utility
Bonneville Power Administration
Entity
BPA
Point of Interconnection
BPA's McNary 230 kV or the proposed Stanfield Substation at 230 kV
Data Source
LBNL
No news available for this project.