— Project Summary

Queue ID
BPA-G0539
Capacity
600 MW
Technology
Solar
Status
active
Location
Crook, OR
Region
West
Developer
IA Status
IA Executed

BetaActiveSolarBPALBNL

600 MW generation in Crook, OR · In queue since May 2016 · Proposed COD March 2022

600 MW

Capacity

1

Components

Solar

9y 10m

In Queue

IA Executed

IA Status

COD target: 2022

Interconnection Timeline

Total Duration

5y 10m

Schedule

49 months past proposed COD

Construction75%
Queue EntryMay 16, 2016

Interconnection request submitted to ISO/RTO

Interconnection Study

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement executed — binding commitment to build

Typical: 30–60 days (negotiation)

ConstructionCurrent

Project under construction

Typical: 12–24 months

Commercial Operation

Proposed COD: 2022-03-31

Project Details

State

OR

County

Crook

Region

West

Developer

Utility

Bonneville Power Administration

Entity

BPA

Point of Interconnection

BPA Ponderosa Substation or on the interconnecting systems tying into the Ponderosa Substation

Data Source

LBNL

No news available for this project.