— Project Summary

Queue ID
BPA-G0537
Capacity
20 MW
Technology
Solar
Status
active
Location
Harney, OR
Region
West
Developer
IA Status
In Progress (unknown study)

BetaActiveSolarBPALBNL

20 MW generation in Harney, OR · In queue since May 2016 · Proposed COD April 2019

20 MW

Capacity

1

Components

Solar

9y 10m

In Queue

In Progress (unknown study)

IA Status

COD target: 2019

Interconnection Timeline

Total Duration

2y 11m

Schedule

85 months past proposed COD

In Study38%
Queue EntryMay 12, 2016

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2019-04-01

Project Details

State

OR

County

Harney

Region

West

Developer

Utility

Bonneville Power Administration

Entity

BPA

Point of Interconnection

Line tap into BPA Harney-Brasada 115 kV line

Data Source

LBNL

No news available for this project.