BetaActiveHydroBPALBNL
210 MW generation in Walla Walla, WA · In queue since May 2016 · Proposed COD July 2031
210 MW
Capacity
1
Components
Hydro
9y 10m
In Queue
Facility Study
IA Status
COD target: 2031
Interconnection Timeline
Total Duration
15y 2m
Facilities Study50%
Queue EntryMay 5, 2016
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2031-07-25
Project Details
State
WA
County
Walla Walla
Region
West
Developer
—
Utility
Bonneville Power Administration
Entity
BPA
Data Source
LBNL
No news available for this project.