— Project Summary

Queue ID
BPA-G0535
Capacity
210 MW
Technology
Hydro
Status
active
Location
Walla Walla, WA
Region
West
Developer
IA Status
Facility Study

BetaActiveHydroBPALBNL

210 MW generation in Walla Walla, WA · In queue since May 2016 · Proposed COD July 2031

210 MW

Capacity

1

Components

Hydro

9y 10m

In Queue

Facility Study

IA Status

COD target: 2031

Interconnection Timeline

Total Duration

15y 2m

Facilities Study50%
Queue EntryMay 5, 2016

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2031-07-25

Project Details

State

WA

County

Walla Walla

Region

West

Developer

Utility

Bonneville Power Administration

Entity

BPA

Data Source

LBNL

No news available for this project.