BetaActiveSolarBPALBNL
100 MW generation in Morrow, OR · In queue since March 2016 · Proposed COD June 2017
100 MW
Capacity
1
Components
Solar
10 years
In Queue
Facility Study
IA Status
COD target: 2017
Interconnection Timeline
Total Duration
1y 3m
Schedule
106 months past proposed COD
Facilities Study50%
Queue EntryMar 18, 2016
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2017-06-30
Project Details
State
OR
County
Morrow
Region
West
Developer
—
Utility
Bonneville Power Administration
Entity
BPA
Point of Interconnection
A 115 kV line tap proximate to Tower Road Switch Station.
Data Source
LBNL
No news available for this project.