BetaActiveSolarBPALBNL
105 MW generation in Lake, OR · In queue since February 2016 · Proposed COD April 2019
105 MW
Capacity
1
Components
Solar
10y 1m
In Queue
Facility Study
IA Status
COD target: 2019
Interconnection Timeline
Total Duration
3y 2m
Schedule
85 months past proposed COD
Facilities Study50%
Queue EntryFeb 4, 2016
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2019-04-01
Project Details
State
OR
County
Lake
Region
West
Developer
—
Utility
Bonneville Power Administration
Entity
BPA
Point of Interconnection
Fort Rock Substation
Data Source
LBNL
No news available for this project.