20 MW generation in Wasco, OR · In queue since January 2016 · Proposed COD December 2018
20 MW
Capacity
1
Components
Solar
10y 2m
In Queue
In Progress (unknown study)
IA Status
COD target: 2018
Interconnection Timeline
Total Duration
2y 11m
Schedule
88 months past proposed COD
In Study38%
Queue EntryJan 7, 2016
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2018-12-31
Project Details
State
OR
County
Wasco
Region
West
Developer
—
Utility
Bonneville Power Administration
Entity
BPA
Point of Interconnection
Within 2 miles of Wasco Electric Coop's 69 kV Tygh Valley Substation (Tap or new substation)
Data Source
LBNL