76 MW generation in Morrow, OR · In queue since November 2015 · Proposed COD July 2018
76 MW
Capacity
1
Components
Solar
10y 4m
In Queue
Facility Study
IA Status
COD target: 2018
Interconnection Timeline
Total Duration
2y 8m
Schedule
94 months past proposed COD
Facilities Study50%
Queue EntryNov 13, 2015
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2018-07-01
Project Details
State
OR
County
Morrow
Region
West
Developer
—
Utility
Bonneville Power Administration
Entity
BPA
Point of Interconnection
Alkali-Tower Road 115 kV Tap point or Willow Creek Energy Center 115 kV line tap.
Data Source
LBNL