BetaActiveSolarBPALBNL
20 MW generation in Sherman, OR · In queue since October 2015 · Proposed COD October 2016
20 MW
Capacity
1
Components
Solar
10y 5m
In Queue
In Progress (unknown study)
IA Status
COD target: 2016
Interconnection Timeline
Total Duration
1 year
Schedule
115 months past proposed COD
In Study38%
Queue EntryOct 20, 2015
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2016-10-01
Project Details
State
OR
County
Sherman
Region
West
Developer
—
Utility
Bonneville Power Administration
Entity
BPA
Point of Interconnection
Iberdrola's Schoolhouse Substation at 230 kV
Data Source
LBNL
No news available for this project.