— Project Summary

Queue ID
BPA-G0516
Capacity
20 MW
Technology
Solar
Status
active
Location
Sherman, OR
Region
West
Developer
IA Status
In Progress (unknown study)

BetaActiveSolarBPALBNL

20 MW generation in Sherman, OR · In queue since October 2015 · Proposed COD October 2016

20 MW

Capacity

1

Components

Solar

10y 5m

In Queue

In Progress (unknown study)

IA Status

COD target: 2016

Interconnection Timeline

Total Duration

1 year

Schedule

115 months past proposed COD

In Study38%
Queue EntryOct 20, 2015

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2016-10-01

Project Details

State

OR

County

Sherman

Region

West

Developer

Utility

Bonneville Power Administration

Entity

BPA

Point of Interconnection

Iberdrola's Schoolhouse Substation at 230 kV

Data Source

LBNL