— Project Summary

Queue ID
BPA-G0513
Capacity
20 MW
Technology
Solar
Status
active
Location
Morrow, OR
Region
West
Developer
IA Status
In Progress (unknown study)

BetaActiveSolarBPALBNL

20 MW generation in Morrow, OR · In queue since September 2015 · Proposed COD December 2016

20 MW

Capacity

1

Components

Solar

10y 6m

In Queue

In Progress (unknown study)

IA Status

COD target: 2016

Interconnection Timeline

Total Duration

1y 3m

Schedule

112 months past proposed COD

In Study38%
Queue EntrySep 18, 2015

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2016-12-31

Project Details

State

OR

County

Morrow

Region

West

Developer

Utility

Bonneville Power Administration

Entity

BPA

Point of Interconnection

115 kV line tap proximate to Tower Road Switch Station

Data Source

LBNL

No news available for this project.