BetaActiveGasBPALBNL
1,100 MW generation in Klamath, OR · In queue since October 2014 · Proposed COD July 2018
1,100 MW
Capacity
1
Components
Gas
11y 5m
In Queue
Facility Study
IA Status
COD target: 2018
Interconnection Timeline
Total Duration
3y 9m
Schedule
94 months past proposed COD
Facilities Study50%
Queue EntryOct 13, 2014
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2018-07-01
Project Details
State
OR
County
Klamath
Region
West
Developer
—
Utility
Bonneville Power Administration
Entity
BPA
Point of Interconnection
Captain Jack 500 kV Substation
Data Source
LBNL