BetaActiveHydroBPALBNL
345 MW generation in Douglas, WA · In queue since July 2013 · Proposed COD January 2022
345 MW
Capacity
1
Components
Hydro
12y 8m
In Queue
Facility Study
IA Status
COD target: 2022
Interconnection Timeline
Total Duration
8y 6m
Schedule
51 months past proposed COD
Facilities Study50%
Queue EntryJul 5, 2013
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2022-01-02