— Project Summary

Queue ID
BPA-G0490
Capacity
345 MW
Technology
Hydro
Status
active
Location
Douglas, WA
Region
West
Developer
IA Status
Facility Study

BetaActiveHydroBPALBNL

345 MW generation in Douglas, WA · In queue since July 2013 · Proposed COD January 2022

345 MW

Capacity

1

Components

Hydro

12y 8m

In Queue

Facility Study

IA Status

COD target: 2022

Interconnection Timeline

Total Duration

8y 6m

Schedule

51 months past proposed COD

Facilities Study50%
Queue EntryJul 5, 2013

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2022-01-02

Project Details

State

WA

County

Douglas

Region

West

Developer

Utility

Bonneville Power Administration

Entity

BPA

Data Source

LBNL

No news available for this project.