— Project Summary

Queue ID
BPA-G0435
Capacity
238 MW
Technology
Wind
Status
active
Location
Morrow, OR
Region
West
Developer
IA Status
Facility Study

BetaActiveWindBPALBNL

238 MW generation in Morrow, OR · In queue since August 2010 · Proposed COD November 2013

238 MW

Capacity

1

Components

Wind

15y 7m

In Queue

Facility Study

IA Status

COD target: 2013

Interconnection Timeline

Total Duration

3y 3m

Schedule

151 months past proposed COD

Facilities Study50%
Queue EntryAug 28, 2010

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2013-11-01

Project Details

State

OR

County

Morrow

Region

West

Developer

Utility

Bonneville Power Administration

Entity

BPA

Point of Interconnection

New substation on 500 kV McNary-HPP Line

Data Source

LBNL

No news available for this project.