BetaActiveWindBPALBNL
238 MW generation in Morrow, OR · In queue since August 2010 · Proposed COD November 2013
238 MW
Capacity
1
Components
Wind
15y 7m
In Queue
Facility Study
IA Status
COD target: 2013
Interconnection Timeline
Total Duration
3y 3m
Schedule
151 months past proposed COD
Facilities Study50%
Queue EntryAug 28, 2010
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2013-11-01
Project Details
State
OR
County
Morrow
Region
West
Developer
—
Utility
Bonneville Power Administration
Entity
BPA
Point of Interconnection
New substation on 500 kV McNary-HPP Line
Data Source
LBNL
No news available for this project.