— Project Summary

Queue ID
BPA-G0368
Capacity
101 MW
Technology
Solar
Status
active
Location
Wasco, OR
Region
West
Developer
IA Status
Facility Study

BetaActiveSolarBPALBNL

101 MW generation in Wasco, OR · In queue since June 2009 · Proposed COD August 2013

101 MW

Capacity

1

Components

Solar

16y 9m

In Queue

Facility Study

IA Status

COD target: 2013

Interconnection Timeline

Total Duration

4y 2m

Schedule

154 months past proposed COD

Facilities Study50%
Queue EntryJun 1, 2009

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2013-08-01

Project Details

State

OR

County

Wasco

Region

West

Developer

Utility

Bonneville Power Administration

Entity

BPA

Data Source

LBNL

No news available for this project.