BetaActiveSolarBPALBNL
202 MW generation in Wasco, OR · In queue since June 2009 · Proposed COD December 2012
202 MW
Capacity
1
Components
Solar
16y 9m
In Queue
Facility Study
IA Status
COD target: 2012
Interconnection Timeline
Total Duration
3y 6m
Schedule
162 months past proposed COD
Facilities Study50%
Queue EntryJun 1, 2009
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2012-12-01
Project Details
State
OR
County
Wasco
Region
West
Developer
—
Utility
Bonneville Power Administration
Entity
BPA
Data Source
LBNL
No news available for this project.