— Project Summary

Queue ID
BPA-G0366
Capacity
302 MW
Technology
Wind
Status
active
Location
Morrow, OR
Region
West
Developer
IA Status
Facility Study

BetaActiveWindBPALBNL

302 MW generation in Morrow, OR · In queue since May 2009 · Proposed COD November 2014

302 MW

Capacity

1

Components

Wind

16y 10m

In Queue

Facility Study

IA Status

COD target: 2014

Interconnection Timeline

Total Duration

5y 6m

Schedule

139 months past proposed COD

Facilities Study50%
Queue EntryMay 19, 2009

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2014-11-01

Project Details

State

OR

County

Morrow

Region

West

Developer

Utility

Bonneville Power Administration

Entity

BPA

Point of Interconnection

A 230 kV substation on BPA's Transmission system in Gilliam or Morrow Co. Ore. near or west of Boardman

Data Source

LBNL

No news available for this project.