— Project Summary

Queue ID
BPA-G0363
Capacity
204 MW
Technology
Wind
Status
active
Location
Gilliam, OR
Region
West
Developer
IA Status
Facility Study

BetaActiveWindBPALBNL

204 MW generation in Gilliam, OR · In queue since April 2009 · Proposed COD November 2012

204 MW

Capacity

1

Components

Wind

16y 11m

In Queue

Facility Study

IA Status

COD target: 2012

Interconnection Timeline

Total Duration

3y 7m

Schedule

163 months past proposed COD

Facilities Study50%
Queue EntryApr 3, 2009

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2012-11-01

Project Details

State

OR

County

Gilliam

Region

West

Developer

Utility

Bonneville Power Administration

Entity

BPA

Point of Interconnection

BPA's Boardman 230 kV Substation

Data Source

LBNL

No news available for this project.