204 MW generation in Gilliam, OR · In queue since April 2009 · Proposed COD November 2012
204 MW
Capacity
1
Components
Wind
16y 11m
In Queue
Facility Study
IA Status
COD target: 2012
Interconnection Timeline
Total Duration
3y 7m
Schedule
163 months past proposed COD
Facilities Study50%
Queue EntryApr 3, 2009
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2012-11-01
Project Details
State
OR
County
Gilliam
Region
West
Developer
—
Utility
Bonneville Power Administration
Entity
BPA
Point of Interconnection
New Substation near McNary 500 kV
Data Source
LBNL