201 MW generation in Wasco, OR · In queue since September 2008 · Proposed COD August 2010
201 MW
Capacity
1
Components
Wind
17y 6m
In Queue
Facility Study
IA Status
COD target: 2010
Interconnection Timeline
Total Duration
1y 11m
Schedule
190 months past proposed COD
Facilities Study50%
Queue EntrySep 16, 2008
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2010-08-30
Project Details
State
OR
County
Wasco
Region
West
Developer
—
Utility
Bonneville Power Administration
Entity
BPA
Data Source
LBNL
No news available for this project.