— Project Summary

Queue ID
BPA-G0344
Capacity
488 MW
Technology
Wind
Status
active
Location
Gilliam, OR
Region
West
Developer
IA Status
Facility Study

BetaActiveWindBPALBNL

488 MW generation in Gilliam, OR · In queue since September 2008 · Proposed COD April 2024

488 MW

Capacity

1

Components

Wind

17y 6m

In Queue

Facility Study

IA Status

COD target: 2024

Interconnection Timeline

Total Duration

15y 7m

Schedule

23 months past proposed COD

Facilities Study50%
Queue EntrySep 4, 2008

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2024-04-30

Project Details

State

OR

County

Gilliam

Region

West

Developer

Utility

Bonneville Power Administration

Entity

BPA

Point of Interconnection

Ashe-Marion 500kV #1

Data Source

LBNL