— Project Summary

Queue ID
BPA-G0295
Capacity
250 MW
Technology
Wind
Status
active
Location
Columbia, WA
Region
West
Developer
IA Status
IA Executed

BetaActiveWindBPALBNL

250 MW generation in Columbia, WA · In queue since October 2007 · Proposed COD December 2011

250 MW

Capacity

1

Components

Wind

18y 5m

In Queue

IA Executed

IA Status

COD target: 2011

Interconnection Timeline

Total Duration

4y 2m

Schedule

173 months past proposed COD

Construction75%
Queue EntryOct 26, 2007

Interconnection request submitted to ISO/RTO

Interconnection Study

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement executed — binding commitment to build

Typical: 30–60 days (negotiation)

ConstructionCurrent

Project under construction

Typical: 18–36 months

Commercial Operation

Proposed COD: 2011-12-31

Project Details

State

WA

County

Columbia

Region

West

Developer

Utility

Bonneville Power Administration

Entity

BPA

Point of Interconnection

Central Ferry Substation

Data Source

LBNL

No news available for this project.