— Project Summary

Queue ID
BHP-BHBE G25
Capacity
115 MW
Technology
Other
Status
active
Location
Pennington, SD
Region
West
Developer
Black Hills Power Inc.
IA Status
Cluster Study

BetaActiveOtherBHPLBNL

115 MW generation in Pennington, SD · In queue since June 2024 · Proposed COD June 2026

115 MW

Capacity

1

Components

Other

1y 9m

In Queue

Cluster Study

IA Status

COD target: 2026

Interconnection Timeline

Total Duration

2 years

Impact Study25%
Queue EntryJun 13, 2024

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2026-06-06

Project Details

State

SD

County

Pennington

Region

West

Developer

Black Hills Power Inc.

Utility

Black Hills Power

Entity

BHP

Point of Interconnection

Lange Substation

Data Source

LBNL