— Project Summary

Queue ID
BHP-BHBE G23
Capacity
110 MW
Technology
Solar
Status
active
Location
Oglala Lakota, SD
Region
West
Developer
IA Status
IA Executed

BetaActiveSolarBHPLBNL

110 MW generation in Oglala Lakota, SD · In queue since November 2022 · Proposed COD December 2026

110 MW

Capacity

1

Components

Solar

3y 4m

In Queue

IA Executed

IA Status

COD target: 2026

Interconnection Timeline

Total Duration

4y 1m

Construction75%
Queue EntryNov 8, 2022

Interconnection request submitted to ISO/RTO

Interconnection Study

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement executed — binding commitment to build

Typical: 30–60 days (negotiation)

ConstructionCurrent

Project under construction

Typical: 12–24 months

Commercial Operation

Proposed COD: 2026-12-01

Project Details

State

SD

County

Oglala Lakota

Region

West

Developer

Utility

Black Hills Power

Entity

BHP

Point of Interconnection

West Hill - South Rapid City

Data Source

LBNL